Analysis of Heavy Equipment Combination in Embankment Work in the Yogyakarta- Bawen Toll Road Project
Loading...
Files
Date
Authors
Journal Title
Journal ISSN
Volume Title
Publisher
Universitas Islam Indonesia
DOI
Abstract
The development of toll road infrastructure in Indonesia continues to grow rapidly to support
national connectivity, including the Yogyakarta–Bawen Toll Road as one of the National Strategic
Projects. In this project, embankment work is a crucial stage that requires the use of heavy equipment
with high productivity. The proper selection of equipment type and combination is essential to ensure
efficiency in terms of time and cost. However, variations in soil conditions, cycle time, and
equipment availability often affect the overall performance. Therefore, this study was conducted to
analyze the productivity of heavy equipment, evaluate alternative equipment combinations, and
determine the most effective option for optimizing both duration and cost of the project.
This research employed a field study approach through direct observations and data
collection at the Yogyakarta–Bawen Toll Road Project, Section 1. The primary data consisted of
cycle time and idle time measurements for excavators, dump trucks, bulldozers, sheepsfoot rollers,
and vibratory rollers, which were recorded using a Stopwatch Time Study and Work Sampling over
five working days. Secondary data, including embankment volume, project layout, and rental costs,
were obtained from the contractor. Productivity was then calculated based on cycle time, efficiency
factors, and equipment capacity. Three alternative equipment combinations were analyzed and
compared to the existing condition to identify the most effective balance between duration and cost.
The results show that the existing combination required 107 working days at a total cost of
Rp1,651,195,200. Alternative 1 reduced the duration to 82 days, Alternative 2 to 55–56 days, and
Alternative 3 to 41 days. Although the alternatives required slightly higher costs (ranging from
Rp1,652,327,000 to Rp1,658,685,000), the time savings were significant. Among the options,
Alternative 3, which employed 4 excavators, 48 dump trucks, 3 bulldozers, 2 sheepsfoot rollers, and
2 vibratory rollers, was identified as the most suitable in terms of project duration. Conversely,
Alternative 1 provided the most cost-efficient solution. These findings indicate a trade-off between
time and cost, allowing decision-makers to select the appropriate alternative based on project
priorities.